Percent-done indicator doesn't count non-worked days
@rmibus
Submitted by Robert Mibus Link to original bug (#320287)
Description
Example:
If I have a task that begins on a Friday, and lasts 5 days (ie. Friday-Thursday in a working week).
I set it to be 20% done (ie. one day)
The little bar that indicates completion ignores that I don't work on the weekend, and indicates on the Monday that I'm behind schedule, even though I'm spot on. (Using the vertical dashed line as 'now' and the dark in-bar line as a "completed" chart).
The downside of fixing this would be that the total real-world time taken would not be correctly indicated (ie, the opposite problem would occur).