Duration unit conversion should be based on calendar
Submitted by Kurt Maute
Link to original bug (#168157)
Description
When entering duration in weeks (in work or lag fields), its converted to days, and is currently hardcoded to 1week = 5 days. Weeks to days conversion should be based on the resource calendar if a resource is assigned, and on the default calendar if no resource is assigned.