Project end date required for ALAP constraints and schedule from end date.
Submitted by Lincoln Phipps
Link to original bug (#138660)
Description
Many projects I do have end dates (or delivery dates) which all tasks should have been completed by.
For planner I envisage an end date for the project which can be used to schedule ALAP (as late as possible) and also help set MFO (Must Finish On) and FNLT (Finish No Later Than) constraints. Projects as a whole should be able to be scheduled from the end date as a project-wide option (basically swapping the time domain around when comparing dates I imagine so may not be too hard to effect).