Dependency lag days does not respect the calendar
Submitted by Beltrachi
Link to original bug (#688832)
Description
The dependency lag should take into account the default calendar and do not count the weekend days as lag days.
Easier to see in an example: You have 2 tasks of 1d work and mark a dependency from A to B with a lag of 3 days.
A -> B (3 days)
The wrong plannig says: Planning (Project starts on Thursday): Thu: A Fri: - Sat: - (weekend) Sun: - (weekend) Mon: B
The plannig should say: Thu: A Fri: - Sat: - (weekend) Sun: - (weekend) Mon: - Tue: - Wed: B