Better view of the tasks when creating a task link
Submitted by Xavier Ordoquy
Link to original bug (#148076)
Description
I'de like to love a nicer tasks vision when it comes to linking tasks within the task dialog. User case: I do manage a team which does pretty the same thing for several packages (let's call them P1/P2/P3) :
- package delivered (milestone)
- installation test
- integration test
so, when I do try to link from the task dialog, I can get severals "intergation test" task but can't figure what package it refers to (or not easily)