Commit 7c72a48c authored by Kurt Maute's avatar Kurt Maute

On summary tasks, make work equal to the sum of child tasks' work.

New function to ensure duration on summary tasks uses the project calendar:
mrp_task_manager_calculate_summary_duration
parent 8592b17a
......@@ -1646,6 +1646,7 @@ task_manager_do_forward_pass_helper (MrpTaskManager *manager,
sub_start = -1;
sub_work_start = -1;
sub_finish = -1;
work = 0;
child = mrp_task_get_first_child (task);
while (child) {
......@@ -1670,6 +1671,7 @@ task_manager_do_forward_pass_helper (MrpTaskManager *manager,
sub_work_start = MIN (sub_work_start, t2);
}
work += mrp_task_get_work (child);
child = mrp_task_get_next_sibling (child);
}
......@@ -1677,18 +1679,12 @@ task_manager_do_forward_pass_helper (MrpTaskManager *manager,
imrp_task_set_work_start (task, sub_work_start);
imrp_task_set_finish (task, sub_finish);
/* FIXME: should work be the sum of the work of the children
* here? The problem is that summary tasks really display
* duration in the work field. That's why we set duration to the
* same value as work below.
*/
work = mrp_task_manager_calculate_task_work (manager,
duration = mrp_task_manager_calculate_summary_duration (manager,
task,
sub_start,
sub_finish);
imrp_task_set_work (task, work);
imrp_task_set_duration (task, work);
imrp_task_set_duration (task, duration);
} else {
/* Non-summary task. */
t1 = task_manager_calculate_task_start (manager, task);
......@@ -2326,3 +2322,76 @@ mrp_task_manager_calculate_task_work (MrpTaskManager *manager,
return work;
}
/* Calculate summary duration using the project calendar,
ignoring assignments' calendars
*/
gint
mrp_task_manager_calculate_summary_duration (MrpTaskManager *manager,
MrpTask *task,
mrptime start,
mrptime finish)
{
MrpTaskManagerPriv *priv;
mrptime t;
mrptime t1, t2;
gint duration = 0;
MrpCalendar *calendar;
MrpDay *day;
GList *ivals, *l;
MrpInterval *ival;
priv = manager->priv;
if (task == priv->root) {
return 0;
}
if (start == -1) {
start = mrp_task_get_start (task);
}
if (finish <= start) {
return 0;
}
calendar = mrp_project_get_calendar (priv->project);
duration = 0;
/* Loop through the intervals of the calendar and add up the working time, until
* the finish time is hit.
*/
t = mrp_time_align_day (start);
while (t < finish) {
day = mrp_calendar_get_day (calendar, t, TRUE);
ivals = mrp_calendar_day_get_intervals (calendar, day, TRUE);
for (l = ivals; l; l = l->next) {
ival = l->data;
mrp_interval_get_absolute (ival, t, &t1, &t2);
/* Skip intervals that are before the task. */
if (t2 < start) {
continue;
}
/* Stop if the interval starts after the task. */
if (t1 >= finish) {
break;
}
/* Don't add time outside the task. */
t1 = MAX (t1, start);
t2 = MIN (t2, finish);
duration += t2 - t1;
}
t += 24*60*60;
}
return duration;
}
......@@ -81,6 +81,10 @@ gint mrp_task_manager_calculate_task_work (MrpTaskManager *man
MrpTask *task,
mrptime start,
mrptime finish);
gint mrp_task_manager_calculate_summary_duration (MrpTaskManager *manager,
MrpTask *task,
mrptime start,
mrptime finish);
void mrp_task_manager_dump_task_tree (MrpTaskManager *manager);
void mrp_task_manager_dump_task_list (MrpTaskManager *manager);
......